Sunday, October 16, 2011

A Look Ahead: Transbay Demolition and Construction Activities



Weekday Work (10/17/11-10/21/11):

Night Shift - The buttress wall installation operation will continue in the eastern transit center site between Beale and Fremont Streets between the hours of 6:00 AM and 1:00 AM. There will be minimal work on site between 1:00 AM and 6:00 AM. If there is a problem, work on site could extend into the hours of between 1:00 AM and 5:00 AM.

CDSM spoils will be removed from the western transit center site and buttress spoils will be removed from the central transit center site during the night shift from 7:00 PM to 2:30 AM.

Day Shift - All contractors will work between the hours of 7:00 AM and 7:00 PM. Activities will include:

Shoring & Excavation Prep:

Buttress wall installation will continue in the eastern transit center site between Beale and Fremont Streets between the hours of 6:00 AM and 1:00 AM.

Trenching prior to Cement Deep Soil Mixing (CDSM) shoring wall will continue in the central transit center site at Natoma Street between Fremont and First Streets - Day Shift.

Welding of I-beams for installation in the Cement Deep Soil Mixing (CDSM) shoring wall will continue in the central transit center site between Fremont and First Streets - Day Shift.

Cement Deep Soil Mixing (CDSM) shoring wall installation will continue in the western transit center site at Natoma Street between First and Second Streets - Day Shift.

Underground Utilities/Trenching:

First Street (from Mission to Howard Streets): Underground Utilities work will commence on First Street between Mission and Howard Streets - Day Shift. Traffic lanes will be reduced to accommodate this work.

Minna Street (First to Shaw Alley): Pavement restoration work will continue along Minna Street between First and Second Streets - Day Shift.

Natoma Street (between Fremont and First Streets): Trenching work near First Street- Day Shift. Local access to 400 Howard Street is available from Fremont Street.

Beale Street: Underground trenching and utilities work- Day Shift. Traffic lanes will be reduced to accommodate this work.

Mission Street: Potholing work will be performed along Mission Street between Main and Beale Streets - Day Shift.

What to Expect Next Weekend (10/22/11 – 10/23/11):

Eastern Transit Center Site (between Beale and Fremont Streets): Buttress construction is expected to continue in the eastern transit center site Saturday, October 22 and Sunday, October 23 between 6:00 AM and 1:00 AM. Depending upon progress in the coming week, the hours of operation and level of activity may be reduced.

Central Transit Center Site (between Fremont and First Streets): Welding of I-beams for Cement Deep Soil Mixing (CDSM) shoring wall will continue inside the construction fence on Saturday, October 22 - Day Shift.

Western Transit Center Site (between First and Second Streets): Cement Deep Soil Mixing (CDSM) shoring wall installation will continue inside the construction fence at both Minna Street and Natoma Street between First and Second Streets on Saturday, October 22 - Day Shift.

Heavy Equipment moves across on First Street between Mission and Howard Streets will take place from Saturday, October 22 through Tuesday, October 25 between 7:00 PM and 11:00 PM.

Pre-trenching work will continue along Natoma Street between Fremont and First Streets on Saturday, October 22 and Sunday, October 23 - Day Shift.

Pavement restoration work will continue along Natoma Street between First and Second Streets on Saturday, October 22 and Sunday, October 23 - Day Shift.

Detours, Street and Sidewalk Closures:

The following streets will be temporarily impacted due to project activities. So you can plan ahead please review the affected streets below:

Minna Street: Between First and Second Streets has been reduced to one lane, one way (west bound) with all vehicles coming in from First Street. Next week, beginning Monday, October 17 there will be a detour with the First Street entrance closed. Minna Street access will be from Shaw Alley exiting at Second Street.

Natoma Street (Between Fremont and First Streets): Natoma Street will be closed at First Street with all vehicles entering from Fremont Street. Local access to 400 Howard Street is available from Fremont Street.

Natoma Street (Between First and Second Streets): Natoma Street has been changed to a dead end street for the life of the project with no vehicle access to Natoma Street from Second Street. Local pedestrian access from Second Street to businesses on Natoma Street will remain available. Local access to 500 Howard Street is available to and from First Street.

First Street: Lane restrictions will be in effect on First Street between Mission and Howard Streets from 7:00 AM to 3:00 PM. SFPD will be on site. The eastern sidewalk is also affected and pedestrians must use the temporary sidewalk in the parking lane on the west side of First Street until further notice.

Fremont Street: Lane restrictions will be in effect on Fremont Street between Mission and Howard Streets from 9:00 AM to 5:00 PM. SFPD will be on site. The east sidewalk of Fremont Street between Mission and Howard Streets will remain closed. Next week the western sidewalk is affected and pedestrians must use the temporary sidewalk in the parking lane on the west side of Fremont Street until end of the week.

Beale Street: Lane restrictions will be in effect on Beale Street between Mission and Howard Streets from 9:00 AM to 3:00 PM. SFPD will be on site.

Market Street and Mission Street: Potholing work will be performed along Mission and Market Street between Main and First Streets from 9:00 AM to 3:00 PM.

PG&E is performing night work along Beale Street between Market and Mission Streets, which will continue into November. This work will result in lane restrictions along Beale Street and is not under the control or authority of the TJPA.

Questions?

Should you have any general questions about the Transbay Transit Center Project, please call Adam Alberti or Stephanie Reichin, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org

Construction Hotline:
If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).

Website:

Please continue to check our website for the most up to date schedule of activities at: http://transbaycenter.org/construction-updates

Construction Activity Map: Check out the construction activity map at: http://transbaycenter.org/construction-updates/construction-activity-map

Public Transit:

The TJPA encourages the use of public transportation. Please click on the link provided to assist in all of your public transportation travel needs: http://511.org/ or visit www.temporaryterminal.org