Weekday Work (11/21/11 – 11/23/11):
Night Shift - The buttress wall installation operation will continue in the eastern transit center site between Beale and Fremont Streets between the hours of 6:00 AM and 1:00 AM. There will be minimal work on site between 1:00 AM and 6:00 AM. If there is a problem, work on site could extend into the hours between 1:00 AM and 5:00 AM.
CDSM spoils will be removed from the central transit center sites, while buttress spoils are removed from the eastern transit center site during the night shift from 7:00 PM to 1:00 AM.
Day Shift - All contractors will work between the hours of 7:00 AM and 7:00 PM, except as otherwise noted below. Activities will include:
Buttress, Shoring & Excavation Work:
Buttress Wall: Installation of the buttress wall will continue in the eastern transit center site inside the construction fence between the hours of 6:00 AM and 1:00 AM.
Shoring Wall: Cement Deep Soil Mixing (CDSM) shoring wall will continue in the central transit center site inside the construction fence – Day Shift.
Excavation Work: Excavation for the new Transit Center Building (including demolition of underground structures) will continue through the end of 2014. The excavation will move from the west transit center site and continue to the east end. The contractor will be excavating to an average depth of about 60 to 65 feet. NOTE: While most excavation work will take place during the day shift to begin, excavation, like the Buttress work, will become a 24 hour activity.
Crushed concrete and spoils will be removed from the western transit center site exiting onto Howard Street from a construction gate located near 564 Howard – Day Shift.
Underground Utilities/Trenching:
First Street (Between Mission and Howard Streets): Underground utilities work continues on First Street – Day Shift.
Mission Street (Between Second and Main Streets): Potholing work will be performed along Mission Street – Day Shift.
What to Expect Next Weekend Thanksgiving Holiday (11/24/11 – 11/27/11):
No heavy work is scheduled to take place during Thanksgiving weekend - Thursday, November 24 through Sunday, November 27. Maintenance work will take place within the site.
Detours, Street and Sidewalk Closures:
The following streets will be temporarily impacted due to project activities. So you can plan ahead, please review the affected streets below:
Beale Street (Between Mission and Howard Streets): Sidewalk paving work will take place along Beale Street on Tuesday, November 22 and Wednesday, November 23 from 9:00 AM to 3:00 PM. Pedestrians will be re-directed into the parking lane. A flagger will be on site.
Howard Street (Between First and Second Streets): Sidewalk paving work will take place along a portion of Howard Street on Monday, November 21 and Tuesday, November 22 from 9:00 AM to 3:00 PM. Pedestrians will not be re-directed.
First Street (Between Mission and Howard Streets): Utility work will take place along First Street. Lane restrictions will be in effect from 7:00 AM to 3:00 PM. SFPD will be on site.
Fremont Street (Between Mission and Howard Streets): Street restoration work will take place along Fremont Street on Saturday, November 19 and Monday, November 21. Access to Natoma Street will be maintained at times. A flagger will be on site.
The east sidewalk of Fremont Street between Mission and Howard Streets will remain closed. Pedestrians are directed to the sidewalk on the west side of Fremont Street.
Minna Street (Between First and Second Streets): Minna Street has been reduced to one lane, one way (west bound), all vehicles will enter from First Street or Shaw Alley. There will be no parking along Minna Street between First Street and 130 feet east of Second Street for the life of the project.
Natoma Street (Between First and Second Streets): Natoma Street will be closed to traffic at Second Street on Saturday, November 19 for pavement restoration. Local access will be available.
Natoma Street has been changed to a dead end street for the life of the project with no vehicle access to Natoma Street from Second Street. Local access to 500 Howard Street is available to and from First Street. Local pedestrian access from Second Street to businesses on Natoma Street will remain available.
Natoma Street (Between Fremont and First Streets): Natoma Street has been reduced to one lane, one way (west bound), all vehicles will enter from Fremont Street and exit at First Street for the life of the project.
Market Street and Mission Street: Potholing work will be performed along Mission between Second and Main Streets from 9:00 AM to 3:00 PM.
Beginning Saturday, November 19 PG&E will be performing work at the Beale and Mission Street intersection, with additional night work being performed along Beale Street between Market and Mission Streets. This work is not under the control or authority of the TJPA. If you have any questions surrounding this work please contact PG&E representative Michael Riordan at (415) 973-6201
Transbay Archeology Exhibit Opening
As the construction of the Transbay Transit Center moves ahead, we would like to share with our project neighbors and Bay Area residents some of the amazing artifacts that we have found along the way.
This exhibit will feature a variety of items discovered within the footprint of the project site that illuminate the rich history of San Francisco’s gold rush era. Recovered artifacts show the way residents of the South of Market neighborhood in the 19th century lived, worked and played, including industrial tools, household items and remnants of neighborhood businesses.
Opening:
Friday, December 2, 2011
TIME: 9 AM – 5 PM
201 Mission Street lobby
San Francisco, CA 94105
Questions?
Should you have any general questions about the Transbay Transit Center Project, please call Adam Alberti or Stephanie Reichin, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at:
info@transbaycenter.org
Construction Hotline:
If you have any urgent questions regarding site-specific demolition or construction activities, please call our construction activity number: (415) 409-TJPA (8572).
Website:
Please continue to check our website for the most up to date schedule of activities at:
http://transbaycenter.org/construction-updates
Construction Activity Map: Check out the construction activity map at:
http://transbaycenter.org/construction-updates/construction-activity-map
Public Transit:
The TJPA encourages the use of public transportation. Please click on the link provided to assist in all of your public transportation travel needs:
http://511.org/ or visit
www.temporaryterminal.org