BOMA San Francisco Members:
Weekday Work (7/25/11 – 7/29/11):
Overnight Shift - Work between the hours of 11:00 PM and 07:00 AM. There are no planned activities next week.
Evening Shift - Work between the hours of 7:00 PM and 11:00 PM. There are no planned activities next week.
Day Shift - All contractors will work between the hours of 7:00 AM and 7:00 PM. Activities will include:
Trenching:
Work will continue on both Minna Street between Second and First Streets and on Natoma Street between Fremont and Second Streets - Day Shift.
Shoring & Excavation Prep:
Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue in the east and west transit center sites, while preparation activities will continue in the central and west transit center sites. - Day Shift.
Demolition:
Natoma Street: Demolition clean-up work will continue along Natoma Street and in the lot between Howard and Natoma Streets - Day Shift.
Howard Street: Demolition work will begin on selected buildings along Howard Street and in the lot between Howard and Natoma Streets - Day Shift.
Underground utilities/ trenching work:
Second & Natoma Street Intersection: Underground trenching and utilities work - Day Shift.
Beale Street (from Mission to Howard Streets): Underground trenching and utilities work - Day Shift.
Fremont Street (from Mission to Howard Streets): Underground trenching and utilities work - Day Shift.
Detours, Street and Sidewalk Closures:
The following streets will be temporarily impacted due to project activities. So you can plan ahead please review the affected streets below:
Second Street: Lane restrictions will be in effect on Second Street between Mission and Howard Streets from 9:00 AM to 3:00 PM.
Natoma Street: Only local access will be allowed on Natoma Street. There will be a partial street closure and parking prohibition in effect on Natoma Street between Fremont and First Streets from 7:00 AM to 5:00 PM. All access to Natoma Street between Fremont and First Streets must use First Street.
There will be a partial street closure and parking prohibition in effect on Natoma Street between First and Second Streets from 7:00 AM to 5:00 PM. There will be an SFPD officer or flagger on site to direct access.
Minna Street: Only local access will be allowed on Minna Street between First and Second Streets from 7:00 AM to 5:00 PM. An SFPD officer or flagger will be on site to direct access.
Beale Street: A temporary sidewalk will be provided in the parking lane on the east side of Beale Street between Mission and Howard Streets through Saturday, July 30, 2011. Lane restrictions will remain on Beale Street between Mission and Howard Streets from 9:00 AM to 3:00 PM.
First Street: Temporary sidewalks will be provided in the parking lanes on both sides of First Street between Mission and Howard Streets through Friday, August 5, 2011.
Fremont Street: Lane restrictions will be in effect on Fremont Street between Mission and Howard Streets from 9:00 AM to 5:00 PM. The east sidewalk of Fremont Street between Mission and Howard Streets will remain closed. Pedestrians must use the west side of Fremont Street until further notice.
What to Expect Next Weekend (7/30/11 - 7/31/11):
Fremont Street: Underground sewer work will occur at the intersection of Fremont and Natoma Streets on Saturday, July 30 and Sunday, July 31 from 7:00 AM to 5:00 PM. Lanes will be reduced along Fremont Street to accommodate this work.
Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue at the east transit center site, Saturday, July 30 from 8:00 AM to 7:00 PM between Beale and Fremont Streets.
Questions?
Should you have any general questions about the Transbay Transit Center Project, please call Adam Alberti or Stephanie Reichin, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at:info@transbaycenter.org
Construction Hotline:
If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).
Website:
Please continue to check our website for the most up to date schedule of activities at: http://transbaycenter.org/construction-updates
Public Transit:
The TJPA encourages the use of public transportation. Please click on the link provided to assist in all of your public transportation travel needs: http://511.org/ or visit www.temporaryterminal.org
Weekday Work (7/25/11 – 7/29/11):
Overnight Shift - Work between the hours of 11:00 PM and 07:00 AM. There are no planned activities next week.
Evening Shift - Work between the hours of 7:00 PM and 11:00 PM. There are no planned activities next week.
Day Shift - All contractors will work between the hours of 7:00 AM and 7:00 PM. Activities will include:
Trenching:
Work will continue on both Minna Street between Second and First Streets and on Natoma Street between Fremont and Second Streets - Day Shift.
Shoring & Excavation Prep:
Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue in the east and west transit center sites, while preparation activities will continue in the central and west transit center sites. - Day Shift.
Demolition:
Natoma Street: Demolition clean-up work will continue along Natoma Street and in the lot between Howard and Natoma Streets - Day Shift.
Howard Street: Demolition work will begin on selected buildings along Howard Street and in the lot between Howard and Natoma Streets - Day Shift.
Underground utilities/ trenching work:
Second & Natoma Street Intersection: Underground trenching and utilities work - Day Shift.
Beale Street (from Mission to Howard Streets): Underground trenching and utilities work - Day Shift.
Fremont Street (from Mission to Howard Streets): Underground trenching and utilities work - Day Shift.
Detours, Street and Sidewalk Closures:
The following streets will be temporarily impacted due to project activities. So you can plan ahead please review the affected streets below:
Second Street: Lane restrictions will be in effect on Second Street between Mission and Howard Streets from 9:00 AM to 3:00 PM.
Natoma Street: Only local access will be allowed on Natoma Street. There will be a partial street closure and parking prohibition in effect on Natoma Street between Fremont and First Streets from 7:00 AM to 5:00 PM. All access to Natoma Street between Fremont and First Streets must use First Street.
There will be a partial street closure and parking prohibition in effect on Natoma Street between First and Second Streets from 7:00 AM to 5:00 PM. There will be an SFPD officer or flagger on site to direct access.
Minna Street: Only local access will be allowed on Minna Street between First and Second Streets from 7:00 AM to 5:00 PM. An SFPD officer or flagger will be on site to direct access.
Beale Street: A temporary sidewalk will be provided in the parking lane on the east side of Beale Street between Mission and Howard Streets through Saturday, July 30, 2011. Lane restrictions will remain on Beale Street between Mission and Howard Streets from 9:00 AM to 3:00 PM.
First Street: Temporary sidewalks will be provided in the parking lanes on both sides of First Street between Mission and Howard Streets through Friday, August 5, 2011.
Fremont Street: Lane restrictions will be in effect on Fremont Street between Mission and Howard Streets from 9:00 AM to 5:00 PM. The east sidewalk of Fremont Street between Mission and Howard Streets will remain closed. Pedestrians must use the west side of Fremont Street until further notice.
What to Expect Next Weekend (7/30/11 - 7/31/11):
Fremont Street: Underground sewer work will occur at the intersection of Fremont and Natoma Streets on Saturday, July 30 and Sunday, July 31 from 7:00 AM to 5:00 PM. Lanes will be reduced along Fremont Street to accommodate this work.
Cement Deep Soil Mixing (CDSM) shoring wall installation activities will continue at the east transit center site, Saturday, July 30 from 8:00 AM to 7:00 PM between Beale and Fremont Streets.
Questions?
Should you have any general questions about the Transbay Transit Center Project, please call Adam Alberti or Stephanie Reichin, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at:info@transbaycenter.org
Construction Hotline:
If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).
Website:
Please continue to check our website for the most up to date schedule of activities at: http://transbaycenter.org/construction-updates
Public Transit:
The TJPA encourages the use of public transportation. Please click on the link provided to assist in all of your public transportation travel needs: http://511.org/ or visit www.temporaryterminal.org
No comments:
Post a Comment