Tuesday, May 11, 2010

Central Subway - Updated May 2010 Drilling Schedule




BOMA San Francisco Members:

Please be aware that there have been changes to the Central Subway drilling schedule.  Please read the following notice and the dates in the new scheduled days for drilling.

The San Francisco Municipal Transportation Agency (SFMTA) and PB/Telamon with Treadwell & Rollo will continue drilling operations for supplemental geotechnical investigations; the purpose of which are to provide critical geotechnical and hydro-geologic information needed for final design and pre-construction of the proposed subway tunnel and associated structures.

Here’s the anticipated drilling schedule throughout the month of May:

May 19-20, 2010: Drilling will be on Stockton and Clay in Chinatown during the day.
May 10-13, 2010: Drilling will be on Stockton and O’Farrell (in front of Macy’s) during the day.
May 17-18, 2010: Drilling will be on 4th Street and Folsom on Folsom during the day.
May 24-25, 2010: Drilling will be on Stockton and Market (in front of Virgin) during the day.
May 15-16, 2010: Drilling will be on Stockton and Washington (near the school yard) during the day.

Here are some facts that you should be aware of:
  • Daytime working hours are between 7am-6pm. Evening working hours are from 9pm-5am.
  • Parking spaces will be temporarily closed as needed during drilling.
  • Drilling will be performed using a truck-mounted drill rig, which will remain on the boring location for the duration of drilling.
  • Please expect a minor increase in noise as a result of drilling
For further information or questions regarding the drilling, please contact Brajah Norris at (415) 701-5263.