Weekend Work: The contractor will remove column foundations in the sidewalk area on the south side of Howard Street between Main and Beale Streets adjacent to the Temporary Terminal site. This work will require the closure of the sidewalk and an eastbound traffic lane on Howard Street between Main and Beale Streets.
The contractor will also begin the removal of the ramp over Beale Street, between Mission and Howard Streets this weekend. Due to the demolition of the over-crossing, Beale Street, between Mission and Howard Streets, is scheduled to be closed for the next four consecutive weekends. This weekend's closure will be from Friday, September 17, 2010 at 10:00 PM to Monday, September 20, 2010 at 5:00 AM.
Weekday Work: Weekday work between Monday, September 20, 2010, and Friday, September 24, 2010, will focus on the removal and cleanup of the remaining columns at the northeast corner of Beale and Howard Streets. The contractor will preform preparatory work to aid the continued demolition of the North Beale Over-crossing.
Hours of Work: Weekday demolition will continue between the hours of 6:00 AM and 3:00 PM. Weekend work will be conducted 24 hours a day with a moratorium on jackhammering between the hours of 11:00 PM and 6:00 AM.
Sidewalk Closure: The sidewalk on the south side of Howard (adjacent to the Temporary Terminal), between Main and Beale Streets, will be closed between Friday, September 17, 2010 at 10:00 PM and Monday, September 20, 2010 at 5:00 AM, to allow the demolition of the column foundations. Flaggers will be on-site during work hours. This work will also necessitate the closure of an eastbound traffic lane on Howard Street.
What to Expect Next Weekend (9/24 - 9/27): The contractor will continue the removal of the North Beale Over-crossing, between Mission and Howard Streets. This work will require the closure of Beale Street.
Community Meeting: Thank you to those who attended our last community meeting on September 8, 2010. Please join us for our next community meetings on Wednesday, October 20, 2010 at 12:00 noon and 6:00 PM at 201 Mission Street, Suite 2100.
Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org.