Monday, January 3, 2011

A Look Ahead: Transbay Demolition and Construction Activities




BOMA San Francisco Members:

Weekday Work: Weekday work between Monday, January 3, 2011 and Friday, January 7, 2011 will focus on the continued demolition of the old Terminal building using the wrecking ball. The contractor will work between the hours of 7:00 AM and 11:00 PM.

Street and Sidewalk Closure: Pedestrians will be diverted from the sidewalk on the east side of Fremont Street between Mission and Howard Streets into the east parking lane due to demolition activities occurring nearby. Pedestrian protection will be provided.

Lane restrictions will remain on Minna and Natoma Streets. Lane restrictions will be in effect on both Fremont Street and First Street between Mission and Howard Street between the hours of 7:00 AM and 3:00 PM.

What to Expect Next Weekend (01/08/11 - 01/09/11): Demolition of the old Terminal building using the wrecking ball will take place on Saturday, January 8, 2011.

Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org.

If you have any urgent questions regarding site-specific demolition or construction activities, please call our construction activity number: (415) 409-TJPA ( 8572).

Please continue to check our website for the most up to date schedule of activities at: www.transbaycenter.org/demolition.