BOMA San Francisco Members:
Webcor’s subcontractor, Trinet, will continue utilities work along on Minna Street. Sewer trenching along Minna Street will begin on Monday, January 10, 2011 and will work its way towards Second Street. Due to the trenching, a small portion of Minna Street will be closed entirely, however all affected buildings will be granted full access to their loading docks.
The contractor will work between the hours of 7:00 AM and 11:00 PM.
Street and Sidewalk Closure: The sidewalk on the east side of Fremont Street is closed. Pedestrians must use the west side of Fremont Street. Pedestrian protection will be provided.
Lane restrictions will remain on Natoma Streets. A small portion of Minna will be closed, however all affected buildings will be granted full access to their loading docks. Lane restrictions will be in effect on both Fremont Street and First Street between Mission and Howard Street between the hours of 7:00 AM and 3:00 PM.
What to Expect Next Weekend (01/14/11 - 01/16/11): Demolition of the West Terminal building using the wrecking ball will take place on Saturday, January 15, 2011.
Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org.
If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).
Please continue to check the Transbay Center website for the most up to date schedule of activities at: www.transbaycenter.org/demolition.