Friday, June 10, 2011

A Look Ahead: Transbay Demolition and Construction Activities



BOMA San Francisco Members:

Weekend Work (6/11/11 – 6/12/11):

Beale Street: Underground utility work will continue on Beale Street and between Mission and Howard Streets and at the intersection of Howard and Beale Streets Saturday, June 11 between the hours of 7:00 AM and 5:00 PM. Detours and lane restrictions will be in effect.

Shoring preparation pile pulling and demolition activities will continue in the eastern lots on Saturday, June 11 from 8:00 AM to 5:30 PM between Beale and Fremont Streets.

Minna Street: Underground utility work and paving activities will continue on Minna Street between First and Second Streets Saturday, June 11 from 7:00 AM to 5:00 PM. Local access to Minna Street will be granted.

Overnight Work (6/13/11 – 6/17/11):

Overnight work will take place the evenings of Monday, June 13 through Friday, June 17 and will continue into the subsequent morning. Contractors will move oversized steel beams and heavy equipment from the central transit zone between First and Fremont Streets onto the eastern zone between Fremont and Beale Streets. Due to the length of the beams and the oversized equipment, these activities will be done at night. Additional lighting will be required to safely transport and unload the steel and equipment, and some noise should be expected.

Second Shift/Evening Work (6/13/11 – 6/17/11):

Our contractor will be performing deep shoring wall work at the east transit center site between Beale and Fremont Streets on two shifts between Monday, June 13 and Friday, June 17. Due to the continuous nature of this work, the contractor will work extended hours from 7:00 AM and 11:00 PM. Additional lighting will be required to safely complete the work and some noise should be expected.

Weekday Work (6/13/11 – 6/17/11):

Weekday work will take place between Monday, June 13 and Friday, June 17. All contractors will work between the hours of 7:00 AM and 9:00 PM, except for those operating within the limited scope of work described above. Activities will include:

Trenching: Work will continue at the east, center and west transit center sites.

Work will continue on Natoma Street between Fremont and First Streets through Friday, June 17 between the hours of 7:00 AM and 5:30 PM.

Work will continue across First Street between Mission and Howard Streets and will be between the hours of 7:00 AM and 3:00 PM.

Shoring & Excavation Prep: Work will continue at the east, central and west transit center sites through the end of June between the hours of 7:00 AM and 5:30 PM.

Demolition: Demolition of the old bus ramp footings between Folsom and Harrison Streets will continue through the end of June between the hours of 7:00 AM and 4:00 PM. Demolition work will continue on selected buildings along Natoma Street. The Crusher/Conveyors has been demobilized and is planned to return in August at the west transit center site.

Underground Utilities Work:

Beale Streets (from Mission to Howard Streets): Utility work, and sidewalk and pavement repairs.

Second, First, and Fremont (from Mission to Howard Streets): Utility work, and sidewalk and pavement repairs.

Minna Street (from First to Second Streets): Utility work, and sidewalk and pavement repairs.

Natoma Street (from Fremont to Second Streets): Utility work, and sidewalk and pavement repairs.

Detours, Street and Sidewalk Closures:

The following streets will be temporarily impacted due to project activities. Please review the affected streets below to plan for changes in your vicinity:

Minna Street: Lane restrictions and parking prohibition will continue on Minna between First and Second Street from 7:00 AM to 5:00 PM. Local access to Minna Street will be granted. There will be an SFPD 10B officer or flagger on site to direct access.

Beale Street: Lane restrictions will remain on Beale Street between Mission and Howard Streets between the hours of 9:00 AM and 3:00 PM.

Natoma Street: Lane restrictions and parking prohibition will be in effect on Natoma between First and Fremont Street from 7:00 AM to 5:00 PM. Local access to Natoma Street will be granted. There will be an SFPD 10B officer or flagger on site to direct access.

Harrison Avenue: Street lighting improvements are in progress now at Harrison Avenue between Second and Essex Streets. Pedestrians will be diverted to a temp sidewalk in the parking lane.

Folsom Street: Installation of street lamp concrete foundation completed with permanent street light pole and sidewalk to be restored in late June.

Fremont Street: The east sidewalk of Fremont Street will remain closed. Pedestrians must use the west side of Fremont Street until further notice.

First Street: Lane restrictions will remain on First Street between Mission and Howard Streets between the hours of 7:00 AM and 3:00 PM.

What to Expect Next Weekend (6/18/11 - 6/19/11):

Beale Street: Underground utility work will continue on Beale Street and between Mission and Howard Street and at the intersection of Howard and Beale Streets Saturday, June 18 and Sunday, June 19 between the hours of 7:00 AM and 5:00 PM. Detours and lane restrictions will be in effect.

Minna Street: Underground utility work and paving activities will continue on Minna Street between First and Second Streets Saturday, June 18 from 7:00 AM to 5:00 PM. Local access to Minna Street will be granted.

Shoring preparation and demolition activities will continue in the east lot on Saturday, June 18 from 8:00 AM to 5:30 PM between Beale and Fremont Streets.

Questions?

Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org

Construction Hotline:

If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).

Website:

Please continue to check our website for the most up to date schedule of activities at: http://transbaycenter.org/construction-updates/updates-notices/current-activity

Public Transit:

The TJPA encourages the use of public transportation. Please click on the link provided to assist in all of your public transportation travel needs: http://511.org/ or visit www.temporaryterminal.org