10 Day Look Ahead: Transbay Demolition and Construction Activities




BOMA San Francisco Members:

Weekend Work: This weekend, the demolition contractor will continue demolition of the old Terminal building using the wrecking ball from 7:00 AM to 11:00 PM on Saturday, December 11. No work is planned for this coming Sunday. The contractor does not anticipate working between 11:00 PM and 6:00 AM. However, if work is required, it will not include jack hammering, wrecking ball usage or other excessive noise producing activities.

The final build-out of the Temporary Terminal Phase 2 configuration will be complete this weekend, and will go into operations for AC Transit tomorrow, Saturday, December 11, 2010 and for Muni on December 16, 2010. For more information, visit: www.TemporaryTerminal.org

Please Note: As previously noticed, Natoma Street, between First and Fremont Streets, has been reduced to one single westbound lane. The contractor will work with neighboring tenants to accommodate all deliveries.

Weekday Work: Weekday work between Monday, December 13, 2010, and Friday, December 17, 2010, will focus on the continued demolition of the old Terminal building using the wrecking ball. We expect to use the wrecking ball on the top of the front facade of the old Terminal building as early as Monday morning. The contractor will work between the hours of 7:00 AM and 5:00 PM during the weekday. Lane restrictions will remain on Minna and Natoma Streets.

The Temporary Terminal contractor will perform work on the Main Street median island between the hours of 7:00 AM and 4:00 PM.

Street and Sidewalk Closure: None.

What to Expect Next Weekend (12/17-12/19): 

Next weekend, the contractor will continue demolition of the old Terminal building using the wrecking ball between the hours of 7:00 AM and 11:00 PM, on Saturday, December 18, 2010. No work is scheduled for Sunday, December 19, 2010.

Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org

If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).

Please continue to check our website for the most up to date schedule of activities at: www.transbaycenter.org/demolition.