BOMA San Francisco Members:
Weekday Work (4/11/11 – 4/15/11): Weekday work will take place between Monday, April 11 and Friday, April 15. All contractors will work between the hours of 7:00 AM and 9:00 PM.
East Transit Center demolition will include pile removal activities that will continue through April between the hours of 7:00 AM and 5:00 PM.
Center Transit Center demolition activities will include the filling and grading of the site. These activities will continue until Friday, April 15th between the hours of 7:00 AM and 5:00 PM.
West Transit Center Demolition activities will include the Crusher/Conveyors operation and the filling and grading of the site. These activities will continue until Friday, April 15th between the hours of 7:00 AM and 5:00 PM.
Demolition work will continue on the old bus ramp from Howard Street towards Folsom Street as well as the old bus ramp off Clementina Street. Demolition activities beside Clementina Street and debris processing on these adjacent parcels will continue through the month of April between the hours of 7:00 AM and 5:00 PM.
Underground utilities work will continue on:
Minna Street from First to Second Streets.
Natoma Street from Fremont to Second Streets.
Howard Street from Main to First Streets.
Second, First, Fremont and Beale Streets from Mission to Howard Streets.
Detours, Street and Sidewalk Closure:
Detours: Minna Street will be closed to through traffic at Second Street. Local access will be granted off of First Street and Shaw Alley.
Lane restrictions will remain on Howard Street between Main and First Streets between the hours of 9:00 AM and 3:00 PM.
Lane restrictions will start on Second Street between Mission and Howard Streets between the hours of 9:00 AM and 3:00 PM.
Lane restrictions will remain on First Streets between Mission and Howard Streets between the hours of 7:00 AM and 3:00 PM.
Lane restrictions will remain on Fremont and Beale Streets between Mission and Howard Streets between the hours of 9:00 AM and 3:00 PM.
Sidewalks: The Fremont Street east sidewalk will remain closed. Pedestrians must use the west side of Fremont Street until further notice.
First Street west sidewalk - Pedestrians will continue to be redirected onto a temporary sidewalk in the west parking lane of First Street until Friday, April 15 to allow for the demolition of the remaining portion of the building and construction of a new temporary sidewalk.
What to Expect Next Weekend (4/16/11 - 4/17/11): Demolition of the Folsom Street overpass starts between Essex and Second Streets Saturday, April 16 and Sunday, April 17 from 7:00 AM to 11:00 PM. Folsom Street will be closed to through traffic from 11:00PM to 7:00 AM so demolition processing and clean-up can continue. There will be SFPD Officers directing access at Essex and Second Streets.
The Crusher/Conveyors operation will be in effect in the West Terminal lot on Saturday, April 16 between the hours of 8:00 AM and 5:00 PM.
Underground utility work will continue on Fremont, Beale and Second Streets on Saturday, April 16 between the hours of 8:00 AM and 5:00 PM. Detours and lane restrictions will be in effect.
Should you have any general questions about the Transbay Transit Center Project, please call Courtney Lodato or Adam Alberti, Transbay Outreach Team, at: (415) 227-9700 or via e-mail at: info@transbaycenter.org
If you have any urgent questions regarding site-specific demolition or construction activities, please call the construction activity number: (415) 409-TJPA (8572).
Please continue to check our website for the most up to date schedule of activities at: www.transbaycenter.org/demolition